Metaâs $27 billion AI data center is causing chaos in small town Louisiana
On a recent morning, the AI boom in Richland Parish, a rural county in northeast Louisiana, could be measured in tacos.
Tim and Lindsey Allen were preparing over 1,600 of them with names like âDivine Swineâ (smoked pork), âRighteous Roosterâ (braised chicken), and âGolden Calfâ (brisket), for construction workers building Metaâs massive 2,250-acre, 4-million-square-foot AI data center, Hyperion. Itâs a catering order that would have been unthinkable here just a year ago.
The Allens, parents of five, had long joked about starting a taco joint called Holy Tacos. (Tim is a church administrator and childrenâs pastor at the First Baptist Church in the small Richland Parish town of Rayville.) When Meta announced in December 2024 that it was investing in a $10 billion facility in Richland Parish, its largest data center to date, they saw a rare opening. Thousands of construction workers, theyâd heard, would soon descend on the siteâan unheard-of customer base for this otherwise rural, economically depressed community.
At first, the plan was to park a taco truck at the site. But when Allen learned that the vehicle he had invested in wouldnât be allowed inside the construction zone, he rented a small vacant building in Rayville, pulled the truck inside, and turned it into a makeshift restaurant serving âfood worth praising.â
The risk paid off. Workers coming off 12-hour shifts in safety gear began to stop by for quick, to-go meals. And as Metaâs construction ramped up, the Allens landed recurring catering work with Mortenson, one of the projectâs three major contractors.
âJust this month, we picked up about 10 caterings,â Allen said. Without Meta, he added, the family likely wouldnât have taken the leap. âItâs been a huge blessing for us.â
For Allen and many other local business owners, Metaâs arrival has brought new customers, contracts, and long-deferred opportunities in a parish that had been losing population and jobs for decades.
The outcome has been very different for Katie and Logan Stewart. The coupleâa nurse and a former farmer in their mid-thirties with two childrenâinvested more than $40,000 of their life savings into Opalâs Orange Food Truck after seeing construction workers post on Facebook asking for food options near the Meta site.
It was a high-stakes bet. Logan had recently stepped away from farming land near the project, and the food truckâserving burgers, chicken, gumbo, and rice and beansâseemed like a way to build a new livelihood without leaving the community.
âI think we were like the second or third truck out there,â Katie said. âWhen we first started, we were doing 100 to 120 orders a day.â
But the momentum didnât last. When one of the projectâs main contractors, DPR, brought in an out-of-state catering company to feed workers on-site, much of the foot traffic Opalâs had counted on disappeared. Workers no longer needed to leave the grounds for lunch.
âYou talk about supporting the local community, but then you outsource the work,â Katie said of DPRâs catering decision. âIt felt like a slap in the face.â
The Stewarts couldnât afford the $1,500 to $2,500 monthly fees charged by two new food truck parks located right across the street from the main Meta entrances, so they parked their truck on a friendâs land a short drive away. Orders fell to fewer than 40 a day. In recent weeks, foot traffic picked up after a local independent journalist wrote about Opalâs, and the Stewarts recently landed a catering job with Meta. They say theyâre determined to adapt. âWeâre planning on sticking it out and adjusting where we need to,â Katie said.
Stories like those of the Allens and Logans are playing out across the country, as companies such as Meta, Google, and Amazonâalongside fast-growing AI startups like OpenAI and Anthropicâembark upon an unprecedented AI data center spending spree. Collectively, they are projected to invest roughly $630 billion to $700 billion in 2026 alone, a 62% jump from 2025, with total AI-related data-center capital expenditures expected to reach $5.2 trillion by 2030, driven largely by GPUs and energy infrastructure. These mega-scale projectsâbuilt to power the AI boom and bolster the U.S. race with China for technological dominanceâare helping to grow the U.S. economy, and are being welcomed with open arms by local officials eager for a piece of the economic development these projects promise. A rising tide, they reason, can lift many ships.
And indeed, thereâs historical precedent for this optimism: The frenzied construction of massive AI data centers across the country echoes earlier American boomsâfrom the California Gold Rush to the early oil fields of Texasâwhen fortunes were made by those in the right place at the right time, selling equipment, food, and shelter to the pioneers of new industries. In those eras, local economies thrived on demand for tools, timber, meals, and rooms for laborers chasing the next big thing.
Today, though, in an era of globalization and corporate consolidation, the âpick-and-shovelâ ripple spreads very differently. Many of the materials, logistics, and meals for the site are supplied by out-of-state contractors from places like Texas and Arkansas. And the specialized chips and many components that power Hyperionâs AI servers are manufactured primarily overseas as part of the global semiconductor and IT hardware supply chain.
So for many Richland Parish residents, the experience is less one of opportunity than of spectatorship: watching the bustle of progress unfold nearbyâand suffering through its accompanying headachesâwithout being able to participate or share in its rewards.
Reached for comment, a spokesperson for Meta said it remains âcommitted to supporting local resources and prioritizing local partnerships whenever possible,â including working with local food vendors to supply more than 600 meals daily. But, they explained, âGiven the scale and size of the craft workforce currently at the site, our general contractors needed to find a catering solution that could meet the scale and logistics required to feed thousands of people.â
When Fortune visited the community, residents expressed a worry that the short-term influx of construction workers will reshape their community, raise rents and tear up the countryside, leaving it spoiled when the construction phase ends and the data centers are left to hum away, consuming water and electricity and employing only a few hundred workers. The dynamic is testing long-held assumptions about who actually benefits when a mega-project arrives in town.
Several residents told Fortune the speed at which the Meta deal was made, and its lack of transparency, left them feeling sidelined. Major decisions about land use, tax incentives, and infrastructure were largely finalized before most community members fully understood the projectâs scaleâwhich has also grown into a much larger build-out than originally planned. In October 2025, Meta announced it had entered a joint venture with funds managed by Blue Owl Capital to finance, build, and operate the Hyperion data center campusâan arrangement targeting up to $27 billion in total development costs and suggesting that Hyperion is intended as a long-term, multiphase campus.
Some described the process as emblematic of a long-standing âgood olâ boysâ culture in local developmentâone in which deals are struck by a small circle of political and business leaders, who then benefit from the result.
âThe small businesses who are profitingâŚitâs not a fair game where the best contractor with the best price and the best qualification wins,â said Amber Perez, the local independent journalist who is also a community activist and posts regularly on Facebook about the Meta project. Instead, she said many residents believe the âwinnersâ are those who are politically and economically connected.
But supporters of the project, including local government officials, economic development leaders, and longtime residents, argue that the Meta investment represents a once-in-a-generation opportunity for a region that has struggled with poverty, job loss, and population decline for decades. In their view, the disruption is the visible price of long-overdue capital flowing into a part of the state that has rarely attracted projects of this magnitude. Even if the number of permanent jobs ultimately proves modest compared to the construction surge, they contend that the billions in investment, new infrastructure, workforce training programs, and heightened national attention could help reposition northeast Louisiana for future industry and growth.
A mixed blessing
Driving east on Route 80 toward the Meta site in Holly Ridge, an unincorporated rural community about 15 minutes east of Rayvilleâthe landscape is defined by flat expanses of soybean and cotton fields, punctuated by grain silos, grazing cows, and the occasional tractor.
At Holly Ridge, however, the terrain changes abruptly. Generations of sharecroppers farmed the land, called the Franklin Farms megasite, until 2006, when the Franklin family sold it to the state of Louisiana, which then hoped to attract an auto plant. That was not to be, but Meta entered a long-term lease for the site in 2024 and purchased it in 2025. Since the company broke ground in early 2025, the farmland has been scraped and leveled into a construction site so disorientingly vast, it resembles the early stages of a city rising from the dirt. At five miles long and 1 mile wide at some points, steel frames jut from the ground. Heavy machinery operates around the clock. An endless stream of trucks pours in before sunrise, feeding a project where thousands of workers move through the site in hardhats and neon vests. Residents complain about damage to their vehicles because of rocks kicked up by the trucks hurtling to and from the Meta site.
Something enormous and unfamiliar has landed, seemingly all at once.
A newly-built road leading into Metaâs Hyperion site carries a prescient name: Far Far Away Lane. The nod to Star Wars is intentional, and the landscape does seem like a new frontierârepresenting not just Metaâs stratospheric AI ambitions, but the financial, energy-hungry reality of building the infrastructure that underpins the AI boom.
Before Meta came to town, the biggest claim to fame of Richland Parish, a community where a quarter of residents live under the poverty line, was arguably that country music artist Tim McGraw was born and raised there. Now, residents are living through a seismic shift that has brought new jobs and excitement to some, and stress and disappointment to othersâas well as heavier traffic on rural roads, rising rents, and mounting pressure on housing, utilities, and daily routines in communities unaccustomed to rapid growth. Beyond those immediate disruptions, whether the short-term gains of massive construction translate into lasting opportunity remains an open question.
Meta says the project has already created hundreds of construction jobs and will support thousands more over the buildout, along with a much smaller number of permanent roles once the data center is operationalâthe original announcement said 500. The company has also partnered with a local community college to launch a construction and workforce-training program aimed at preparing residents for jobs tied to the site and future industrial development.
And indeed at Metaâs Hyperion site, as thousands of temporary workers have descended on Richland Parish, taking space in hotels, short-term rentals and newly-built RV parks, there are clear examples of individual businesses booming. GrowNELA, the regional economic development authority for northeast Louisiana, pointed Fortune to companies like ServiceMaster Action Cleaning, a Monroe-based facilities maintenance firm that has doubled its workforce since Meta arrived, and Copeland Electric, another Monroe company that says the project has driven a roughly 40% increase in hiring.
The arrival of the Meta project was a catalyst for Chris Holyfield, the owner of Holy Dippers, a company created specifically to serve the construction project. He supplies septic services and eco-friendly restroom facilities for Meta workersâ58 units so far, with more to be added as construction ramps up.
Holyfield wanted to take advantage of the once-in-a-lifetime opportunity, after leaders from the construction companies working on the Meta project told Holyfield that âthis areaâs about to explode,â he said. âNo one believed it at first,â he explained. âNow weâre all feeling the difference.â
Holyfield also owns three restaurants in Monroe that do catering work for Metaâs large contracting companies, as well as a seven-story office building in Monroe where Meta leased space before the data center announcement was made.
Rob Cleveland, president and CEO of GrowNELA, who arrived in Louisiana in July 2024 after eight years in a similar role in Michigan, dismissed complaints about the level of local job creation as âsilly.â He emphasized that several thousand new jobs have already arrived in the rural Richland Parish communityâboth working on the Meta site and for businesses servicing the site. Jobs are jobs, he arguesâand the pragmatic reality is there arenât many options for a community like Richland Parish.
âConstant naysayers say theyâre short-term jobs, that there will be only 500 long-term jobs, why arenât you recruiting automotive plants with 3000 long-term jobs,â Cleveland said. âWell, those projects donât really exist anymore, and we donât have the labor to support those projects.â
Where will they all live?
The influx of workers has created an immediate, practical problem in Richland Parish: housing. Currently, there are about 3,700 workers connected to the site, with an estimated peak in a couple of months of 5,000 (though locals say they have heard numbers as high as 8,000).
To accommodate the influx of construction workers, a patchwork of RV parks, or âman campsââboth large and smallâhas sprung up across the area. One of Metaâs three primary construction firms, DPR, hired subcontractor Mammoth Industries to build a sprawling, 130-acre workforce housing complex that includes more than 300 full-service RV sites near the Meta project.
And smaller, family-run RV parks are emerging as well. Kayla Caskey, the owner of South Stuart RV Park, about 25 minutes from the Meta site, grew up on the land where the park now sits. âWeâve had it for a couple of generationsâit was passed down from my grandparents,â she said. âI got married and moved away, but my family still lives thereâmy mom and my brotherâand we decided to take advantage of this opportunity.â
South Stuart RV Park has room for just 12 RVs, and Caskey said getting it up and running required navigating zoning rules and installing proper facilities, including showers and bathrooms. âWe learned a lot along the way,â she said. âBut we hope, in the end, this will be something good for our family.â The park filled quickly after opening, she added, and she continues to receive daily inquiries.
Caskey is realistic about the parkâs future once construction winds down. âIt may just be land out there again,â she said. âBut hopefully, over the next couple of years, itâll pay off while the workers are still here.â
But for others, the rapid spread of RV parks in the area has felt disruptive and overwhelming. For example, Fortune visited one mile-long dead-end road that until recently was lined with just eight homes. Now, two large RV parksâtogether expected to add up to 700 hookupsâare under construction on the street, many directly next to or across the street from the few single-family homes.
Other area residents say they are being priced out of the area, or even facing attempted eviction, because of the influx of workers. Erika James, a 34-year-old mother of two who grew up in Richland Parish and now lives in a mobile home park in Monroe, a small regional hub about 30 minutes west of the Meta site, says her rent increased several times over the past six months. Earlier this month she received an eviction notice after paying her rent just one day late, saying her family had just five days to vacate.
âI panicked and my husband immediately called the property owner and was told it had nothing to do with rent,â she said. âIn fact, he said he didnât even agree with the decision but it came from âabove himâ because âthey needed to make room for other tenants.ââ
After agreeing to pay an âeviction fee,â James was able to stay, but she recently received a text saying no leases are being renewed â and hers runs out in April.
âMeanwhile, there is literally a sign outside welcoming Meta workers while local families are left wondering where theyâre supposed to go,â she said. âWe are now having to entertain the idea of leaving the area completely. There is nowhere to go if you canât pay triple prices.â
âIt breaks your heart to even think about having to leave here,â she said. âBut itâs getting more expensive every day.â
The Meta project has promised transformation, explained Perez. But she added many residents of Richland Parish have little clarity about what that transformation will actually look like in the end.
âTransform, how?â she said. âThatâs what people are on the edge of their seats trying to figure out, because right now youâre in the chaos phase where you donât know which way to look, and when the dust settles, whatâs left?â
Perez had heard that some people are âwaiting it outâ because they want to see if they can sell their property when it becomes more valuable. âOthers just want the heck out because they want their quiet life back, and this is not what they signed up for,â she said. âAnd then thereâs others who are just stuck.â
A rural Louisiana parishâs fervid campaign to bring Big Tech to its back roads
In Louisiana, the effort to court Meta for the Richland Parish site began early. According to reporting by the Times Picayune, Entergy Louisiana economic development executive Ed Jimenez and CEO Philip May hosted roughly half a dozen Meta executives at Entergyâs headquarters in New Orleans in early 2024, after May learned the company was searching for a Southern location to build a data center.
This is not unusual: Across the nation, consortia of state governments, utilities, and economic development groups are actively competing to attract tech companies to build AI data centers. For example, OpenAI said it and its partners reviewed more than 300 proposals from over 30 states before selecting five additional sites for its Stargate data center program, following the launch of its flagship facility in Abilene, Texas.
Over dinner, the Meta folks told Entergy that they would consider Louisiana but that the state would have to move fast to come up with a deal. Entergy executives worked with recently-elected Governor Jeff Landry to forge agreements with legislative leaders, cabinet secretaries and local government officials.
Meta ultimately secured significant tax incentives for the project, including a sales tax exemption on the billions of dollars it will spend on servers and equipment. But Meta emphasized that Richland Parish would also reap tax revenue and economic development.
âRichland Parish receives both a portion of sales tax from our construction materials along with a PILOT (payment in lieu of taxes), based on jobs and capital investment,â a Meta spokesperson said.
These PILOT agreementsâcommon in large data center dealsâallow companies to pay a negotiated annual fee instead of full property taxes, with the amount tied to how much they invest and how many jobs they create. Public details of the Richland Parish agreement are limited, but a state contract reviewed by WIRED last year confirmed Metaâs payments and tax breaks are structured around hitting specific investment and hiring thresholds. The Meta spokesperson said the company has invested over $300 million to date in roads, water, and other local infrastructure.
While Louisiana also offers broad sales tax exemptions for data center equipment, local governments can still collect revenue from construction-related spending, because the stateâs âsales and use taxâ system applies taxes based on where materials are ultimately used. The result is a complex mix of long-term tax relief for the company paired with more limited, often temporary, revenue streams for the parish.
Meanwhile, the Hyperion project is already getting even bigger. Even as residents grapple with the disruption of the current buildout, Meta has quietly acquired roughly 1,400 additional acres adjacent to the existing 2,250-acre Hyperion site, according to people affiliated with companies working on or around the project, paving the way for a second phase of expansion. In reporting this story, Fortune observed active work underway on the newly acquired land.
A temporary boom is better than no boom at all
Some local leaders push back on residentsâ complaints that the disruption outweighs the opportunity. GrowNELAâs Cleveland said complaints about traffic and housing are âcompletely valid and understandable,â adding that âitâs happening very quickly and itâs happening exponentially.â But he pointed out that the land used for the Meta site has been marketed as industrial for more than two decades and the state had long hoped for development to come. Those efforts coming to fruition is something to celebrate, not complain about, he argued: âWeâve hit the gold rush.â
Monroe Mayor Friday Ellis, who was elected to a second term in 2024 and sits on GrowNELAâs board, argues that the challenges now surfacing around housing, traffic, and infrastructure are not unique to the Meta projectâbut reflect the challenges of building on a âhyperâ scale in a region that has long lacked investment.
Ellis also says he understands why people are skeptical of the promises Meta and local politicians are making about the development bringing economic opportunity. He grew up in Richland Parish, and was raised by a single father who sharecropped on the land. He said skepticism toward the project is rooted in a history of broken promises. âFor years, theyâve been ignored,â he said. âThey donât believe this is a real opportunity.â
Still, Ellis is unapologetically bullish. He argues that large projects like Metaâs offer a rare chance to change the communityâs trajectory. âThis region has a lot of poverty, and poverty exists because thereâs no opportunity,â he said. âOpportunity and education lift people out of poverty. Our job right now is to connect as many people as possible to opportunity.â
Ellis has described the region as a budding âSilicon Bayou,â and said increased attentionâfrom investors, contractors, and state leadersâhas already begun to unlock new economic activity. âWhat gives me hope,â he said, âis that more people are paying attention to this part of the world.â
The Silicon Bayou label may not be hyperbole for northern Louisiana. The entire northern part of the state is increasingly being marketed as an AI infrastructure hub. In addition to Metaâs Hyperion expansion, Amazon recently announced plans to invest $12 billion in northwest Louisiana to build data center campuses.
And GrowNELAâs Cleveland said that more tech investment is coming to Richland Parish: âWe are actively working on a diverse mix of projects for Richland Parish and the entire region,â he said. âThat mix includes data centers, manufacturing, warehouses and suppliers of the Meta and Amazon data centers.â
But Richland Parish resident Dewanna Sanders, who owns a small food business and lives about three miles from the Meta site, said she was saddened by the changes to the landscape when she leaves her home before sunrise.
âItâs lit up like New York City,â she said of the site, describing it as a âhaloâ she can see from her front steps.
While Sanders acknowledges that the data center will likely be good for the area in the long runâand that both her business and her husbandâs have benefitedâshe said she cried when it was announced.
âItâs not the country anymore,â she said. âEverything is going to change here. Nothingâs going to be the same again.â
Sanders said she has received several offers on her 600-acre property and initially thought she might want to leave. âBut where are you going to go?â she said. âThis is home.â
Even Tim Allen, whose Holy Tacos business has benefited greatly from the Meta project, acknowledges how overwhelming the scale of the construction has been for many in what was once a quiet farming community. âNow itâs lights and noise, day and night,â he says. Still, as a pastor and father, Allen sees the project as a chance for something the region has long lacked. âThere was nothing here for our kids,â he said. âThey were growing up and moving away.âThe Meta site, he believes, offers an opportunity for families to stayâand for the community to adapt. âItâs not going anywhere,â he said. âSo weâre trying to meet it with empathy, figure out how to help the people who are struggling, and ask how we can grow and benefit together.â